Explosion At ThePlanet Datacenter Drops 9,000 Servers

Posted by kdawson on Sun Jun 01, 2008 01:07 PM
from the could-happen-to-anyone dept.
An anonymous reader writes "Customers hosting with ThePlanet, a major Texas hosting provider, are going through some tough times. Yesterday evening at 5:45 pm local time an electrical short caused a fire and explosion in the power room, knocking out walls and taking the entire facility offline. No one was hurt and no servers were damaged. Estimates suggest 9,000 servers are offline, affecting 7,500 customers, with ETAs for repair of at least 24 hours from onset. While they claim redundant power, because of the nature of the problem they had to go completely dark. This goes to show that no matter how much planning you do, Murphy's Law still applies." Here's a Coral CDN link to ThePlanet's forum where staff are posting updates on the outage. At this writing almost 2,400 people are trying to read it.
+ -
story

Related Stories

This discussion has been archived. No new comments can be posted.
The Fine Print: The following comments are owned by whoever posted them. We are not responsible for them in any way.
 Full
 Abbreviated
 Hidden
More
Loading... please wait.
  • by Anonymous Coward on Sunday June 01 2008, @01:11PM (#23618759)
    Electricity is a fickle mistress, one moment she's gently caressing your genitals through gingerly applied electrodes the next she's blowing up your data centers.
  • by QuietLagoon (813062) on Sunday June 01 2008, @01:12PM (#23618761)
    ... for posting frequent updates to the status of the outage.
    • by larien (5608) on Sunday June 01 2008, @01:47PM (#23619065) Homepage Journal
      It's probably less effort to spend a few minutes updating a forum than it would be to man the phones against irate customers demanding their servers be brought back online.
    • Update 11:14 PM CST (Score:4, Informative)

      by Solokron (198043) on Sunday June 01 2008, @11:33PM (#23623161)
      As previously committed, I would like to provide an update on where we stand following yesterday's explosion in our H1 data center. First, I would like to extend my sincere thanks for your patience during the past 28 hours. We are acutely aware that uptime is critical to your business, and you have my personal commitment that The Planet team will continue to work around the clock to restore your service. As you have read, we have begun receiving some of the equipment required to start repairs. While no customer servers have been damaged or lost, we have new information that damage to our H1 data center is worse than initially expected. Three walls of the electrical equipment room on the first floor blew several feet from their original position, and the underground cabling that powers the first floor of H1 was destroyed. There is some good news, however. We have found a way to get power to Phase 2 (upstairs, second floor) of the data center and to restore network connectivity. We will be powering up the air conditioning system and other necessary equipment within the next few hours. Once these systems are tested, we will begin bringing the 6,000 servers online. It will take four to five hours to get them all running. We have brought in additional support from Dallas to have more hands and eyes on site to help with any servers that may experience problems. The call center has also brought in double staff to handle the increase in tickets we're expecting. Hopefully by sunrise tomorrow Phase 2 will be well on its way to full production. Let me next address Phase 1 (first floor) of the data center and the affected 3,000 servers. The news is not as good, and we were not as lucky. The damage there was far more extensive, and we have a bigger challenge that will require a two-step process. For the first step, we have designed a temporary method that we believe will bring power back to those servers sometime tomorrow evening, but the solution will be temporary. We will use a generator to supply power through next weekend when the necessary gear will be delivered to permanently restore normal utility power and our battery backup system. During the upcoming week, we will be working with those customers to resolve issues. We know this may not be a satisfactory solution for you and your business but at this time, it is the best we can do. We understand that you will be due service credits based on our Service Level Agreement. We will proactively begin providing those following the restoration of service, which is our number priority, so please bear with us until this has been completed. I recognize that this is not all good news. I can only assure you we will continue to utilize every means possible to fully restore service. I plan to have an audio update tomorrow evening. Until then, Douglas J. Erwin Chairman & Chief Executive Officer
  • explosion? (Score:5, Funny)

    by Anonymous Coward on Sunday June 01 2008, @01:14PM (#23618775)
    Lesson learned: don't store dynamite in the power room.
  • by z_gringo (452163) <z_gringo@@@hotmail...com> on Sunday June 01 2008, @01:20PM (#23618805)
    At this writing almost 2,400 pelople are trying to read it. Posting it on slashdot should help speed it up.
    • by Lorcas (1299955) on Sunday June 01 2008, @01:47PM (#23619073)
      Here's a new update from Urvish Vashi: To keep you up-to-date, some idiot posted this forum page on slashdot. Expect some slowdowns and interruptions trying to access this page. ps: **** you slashdot.
    • by kyoorius (16808) on Sunday June 01 2008, @05:20PM (#23620695) Homepage
      There's no reason to use the forum software when they've locked the thread and are only using it to disseminate information. A Pentium one running lighttpd serving a static html page would be sufficient to handle the flood of requests.

  • by Scuzzm0nkey (1246094) on Sunday June 01 2008, @01:20PM (#23618809)
    I wonder what the dollar value of the repairs will run? I'm sure insurance covers this kind of thing, but I'd love to see hard figures like in one of those mastercard commercials: Structural damage: $15000 Melted hardware: $70000 Halon refill: $however much halon costs Real-Life Slashdot effect: Priceless
      • Re:Recovery costs (Score:5, Insightful)

        by macx666 (194150) * on Sunday June 01 2008, @01:30PM (#23618893) Homepage

        Not to mention the cost of pulling all those consultants in, overnight, on a weekend...

        Also, only the electrical equipment (and structural stuff) was damaged - networking and customer servers are intact (but without power, obviously).
        I read that they pulled in vendors. Those types would be more than happy to show up at the drop of a hat for some un-negotiated products that insurance will pay for anyway, and they'll even throw in their time for "free" so long as you don't dent their commission.
          • No, not necessarily (Score:5, Informative)

            by Sycraft-fu (314770) on Monday June 02 2008, @01:28AM (#23623757)
            You are probably thinking of auto insurance. Yes, it usually goes up when used. The reason is because when you use it, it is usually because you did something that changed your risk level. If you get in an accident, that makes you a higher risk. Continue to get in accidents, you are a higher risk still. Thus the companies want more money. It's all based on risk calculation. That's also why they want more money when you are under 25. Statistically speaking, young people are a much higher risk of accidents.

            Well with building insurance, that's not the case. You aren't really a significant risk factor. Risk is instead calculated of of things like what kind of structure it is, how far it is from the fire department, what it's used for, what it contains (that determines what they are on the hook for) etc. So when something happens, unless it was because of a previously unknown risk factor, your rates don't necessarily change. Nothing changed with regards to risk.

            Insurance is really all just risk based. They take the probability of having to make a payout and the amount of said payout vs time and come up with a rate. If something changes the risk, the rate will change as well, but if not then it doesn't change. It isn't as though your one single payout is of any significance to their overall operation.

            Also, the idea of "Just pay for it yourself," is extremely silly. It smacks of someone who's never owned something of any significant value. The reason behind insurance is that you CAN'T just pay for it yourself. For example I have insurance on my house. The reason is that if I lost it, I can't afford to replace it. I don't have a couple hundred grand just lying around in the bank. That's the point of insurance. You are insuring that if something happens that you can't afford, someone will pay for it. The insurance company is then, of course, that it isn't likely to happen and they get to keep the money.
  • Clearly this is bad karma resulting from all their years of human rights violations....especially Tiananmen Square...oh wait--
  • by Pyrex5000 (1038438) on Sunday June 01 2008, @01:22PM (#23618835)
    I blame Kevin Hazard.
  • by quonsar (61695) on Sunday June 01 2008, @01:22PM (#23618839) Homepage
    At this writing almost 2,400 people are trying to read it

    and as of this posting, make that 152,476.
  • by PPH (736903) on Sunday June 01 2008, @01:26PM (#23618855)

    Being in the power systems engineering biz, I'd be interested in some more information on the type of building (age, original occupancy type, etc.) involved.

    To date. I've seen a number of data center power problems, from fires to isolated, dual source systems that turned out not to be. It raises the question of how well the engineering was done for the original facility, or the refit of an existing one. Or whether proper maintenance was carried out.

    From TFA:

    electrical gear shorted, creating an explosion and fire that knocked down three walls surrounding their electrical equipment room.
    Properly designed systems should never result in any fault to become uncontained in this manner.
      • by p0tat03 (985078) on Sunday June 01 2008, @01:49PM (#23619091)

        I'm a mechanical/electrical engineer by training, and what you're saying makes no sense to us. Mistakes are made in the laboratory, where things are allowed to blow up and start fires. Once you hit the real world the considerations are *very different*. While it's possible that this fire could be caused by something entirely unforeseeable (unlikely given our experience in this field), it's also possible that this was due to improperly designed systems.

        I don't suppose you'd be singing the same tune if this was a bridge collapse that killed hundreds. There's a reason why engineering costs a lot, and that's directly correlated to how little failure we can tolerate.

  • Explosion? (Score:4, Insightful)

    by mrcdeckard (810717) on Sunday June 01 2008, @01:30PM (#23618891) Homepage

    The only thing that I can imagine that could've caused an explosion in a datacenter is a battery bank (the data centers I've been in didn't have any large A/C transformers inside). And even then, I thought that the NEC had some fairly strict codes about firewalls, explosion-proof vaults and the like.

    I just find it curious, since it's not unthinkable that rechargeable batteries might explode.

    mr c
    • Re:Explosion? (Score:5, Informative)

      by Gazzonyx (982402) on Sunday June 01 2008, @01:54PM (#23619137)
      Actually, modern batteries should be sealed valve or Absorbed Glass Mat (AGM) that don't vent (too much) hydrogen. During a thermal runaway, they vent a tiny bit before killing themselves, but hydrogen doesn't become explosive until the concentration in an enclosed environment is ~4%. 4% of a data center is a fairly large area. I've heard of this happening in one data center where the primary and fail over (IIRC) HVAC units failed and no one had been on site for well over a month. IOW, every battery in the place started venting and it took over a month without any air circulation for it to get to 4%.
    • Re:Explosion? (Score:4, Insightful)

      by RGRistroph (86936) <rgristroph@yahoo.com> on Sunday June 01 2008, @02:07PM (#23619221) Homepage
      Haven't you ever seen one of those gray garbage can sized transformers on a pole explode ? I used to live in a neighborhood that was right across the tracks from some sort of electrical switching station or something, they had rows of those things in a lot covered with white gravel. Explosions that were violent enough to feel like a granade going off a hundred yards away were not uncommon. I think most of them were simply the arcing of high voltage vaporizing everything and producing a shock wave, but sometimes the can-type transformers that are filled with cooling oil exploded and the burning oil sprayed everywhere.

      At one place I worked, every lightening storm my boss would rush to move his shitty old truck to underneath the can on the power pole, hoping the thing would blow and burn it so he could get insurance to replace it.
  • by martyb (196687) on Sunday June 01 2008, @01:30PM (#23618897)

    Kudos to them for their timely updates as to system status. Having their status page listed on /. doesn't help them much, but I was encouraged to see a Coral Cache link to their status page. In that light, here's: a link to the Coral Cache lofiversion of their status page:

    • http://forums.theplanet.com.nyud.net:8080/lofiversion/index.php/t90185.html
  • by cptnapalm (120276) on Sunday June 01 2008, @02:06PM (#23619209)
    They need to build the building out of what ever they build the servers out of.
  • by Sentry21 (8183) on Sunday June 01 2008, @02:27PM (#23619379) Journal

    electrical gear shorted, creating an explosion and fire that knocked down three walls surrounding their electrical equipment room.
    But the fourth wall stayed up! And that's what you're getting, son - the strongest data centre in all of Texas!

  • Everyone loves firemen, right? Not me. While the guys you see in the movies running into burning buildings might be heroes, the real world firemen (or more specifically fire chiefs) are capricious, arbitrarty, ignorant little rulers of their own personal fiefdom. Did you know that if you are getting an inspection from your local firechief and he commands something, there is no appeal? His word is law, no matter how STUPID or IGNORANT. I'll give you some examples later.

    I'm one of the affected customers. I have about 100 domains down right now because both my nameservers were hosted at the facility, as is the control panel that I would use to change the nameserver IPs. Whoops. So I learned why I need to obviously have NS3 and ND4 and spread them around because even though the servers are spread everywhere, without my nameservers none of them currently resolve.

    It sounds like the facility was ordered to cut ALL power because of some fire chief's misguided fear that power flows backwards from a low-voltage source to a high-voltage one. I admit I don't know much about the engineering of this data center, but I'm pretty sure the "Y" junction where AC and generator power come together is going to be as close to the rack power as possible to avoid lossy transformation. It makes no sense why they would have 220 or 400 VAC generators running through the same high-voltage transformer when it would be far more efficient to have 120 or even 12VCD (if only servers would accept that). But I admit I could be wrong, and if it is a legit safety issue...then it's apparently a single point of failure for every data center out there because ThePlanet charged enough that they don't need to cut corners.

    Here's a couple of times that I've had my hackles raised by some fireman with no knowledge of technology. The first was when we switched alarm companies and required a fire inspector to come and sign off on the newly installed system. The inspector said we needed to shut down power for 24 hours to verify that the fire alarm would still work after that period of time (a code requirement). No problem, we said, reaching for the breaker for that circuit.

    No no, he said. ALL POWER. That meant the entire office complex, some 20-30 businesses, would need to be without power for an entire day so that this fing idiot could be sure that we weren't cheating by sneaking supplimentary power from another source.

    WHAT THE FRACK

    We ended up having to rent generators and park them outside to keep our racks and critical systems running, and then renting a conference room to relocate employees. We went all the way to the country commmissioners pointing out how absolutely stupid this was (not to mention, who the HELL is still going to be in a burning building 24 hours after the alarm's gone off) but we told that there was no override possible.

    The second time was at a different place when we installed a CO alarm as required for commercial property. Well, the inspector came and said we need to test it. OK, we said, pressing the test button. No no, he said, we need to spray it with carbon monoxide.

    Where the HELL can you buy a toxic substance like carbon monoxide, we asked. Not his problem but he wouldn't sign off until we did. After finding out that it was illegal to ship the stuff, and that there was no local supplier, we finally called the manufacturer of the device who pointed out that the device was void the second it was exposed to CO because the sensor was not reusuable. In other words, when the sensor was tripped, it was time to buy a new monitor. You can see the recursive loop that would have devloped if we actually had tested the device and then promptly had to replace it and get the new one retested by this idiot.

    So finally we got a letter from the manufacturer that pointed out the device was UL certified and that pressing the test button WAS the way you tested the device. It took four weeks of arguing before he finally found an excuse that let him safe face and
    • Look, when I go into a building in gear and carrying an axe and an extinguisher, breathing bottled air, wading through toxic smoke I couldn't give crap number one about your 100 sites being down.

      I have a crew to protect. In this case, I'm going into an extremely hazardous environment. There has already been one explosion. I don't know what I'm going to see when I get there, but I do know that this place is wall to wall danger. Wires everywhere to get tangled in when its dark and I'm crawling through the smoke. Huge amounts of currents. Toxic batteries everywhere that may or may not be stable. Wiring that may or may not be exposed.

      If its me in charge, and its my crew making entry, the power is going off. Its getting a lock-out tag on it. If you wont turn it off, I will. If I do it, you won't be turning it on so easily. If need be, I will have the police haul you away in cuffs if you try to stop me.

      My job, as a firefighter -- as a fire officer -- is to ensure the safety of the general public, of my crew, and then if possible of the property.

      NOW -- As a network guy and software developer -- I can say that if you're too short sighted or cheap to spring for a secondary DNS server at another facility, or if your servers are so critical to your livelihood that losing them for a couple of days will kill you but you haven't bothered to go with hot spares at another data center then you sir, are an idiot.

      At any data center - anywhere - anything can happen at any time. The f'ing ground could open up and swallow your data center. Terrorists could target it because the guy in the rack next to yours is posting cartoon photos of their most sacred religious icons. Monkeys could fly out of the site admin's [nose] and shut down all the servers. Whatever. If its critical, you have off site failover. If not, you're not very good at what you do.

      End of rant.
            • Not so simple. (Score:5, Informative)

              by CFD339 (795926) <andrewp@@@thenorth...com> on Monday June 02 2008, @12:48AM (#23623561) Homepage Journal
              While it sounds like a reasonable approach at first, it makes assumptions that I can't make as an officer on scene.

              1. It assumes that the only problem is with the original transformer. When I arrive on scene I don't know what the problem was -- even if you tell me you do know, I can't believe it. I also don't know what the secondary problems are.

              2. Feeding power into a building that has been physically damaged is very very dangerous. We're not talking about a transformer "failing to work" we're talking about something that blew the walls off the room it was in.

              3. We already know that things didn't go the way they were supposed to. Something failed. Some safety plan didn't work. We have to assume that we're dealing with chaos until proved otherwise.

              So, as a fire officer I arrive on scene and have a smoke filled building with reports of an explosion and MAYBE a report that everyone is out. I need to go in and find out what happened, if anything is still burning or in immediate danger, and if anyone is still in side. To do that safely, the first thing I want to do is secure the power to the building (shut it off) as well as any other utility feeds (oil, steam, liquefied petroleum or natural gas).

              The gear I carry -- even the radio -- is designed to never create even the tiniest spark in its operation. We call it "intrinsically safe". Its one of a great many precautions we take.

              We go in to a place like this not knowing the equipment, not knowing its condition.

              My final proof point --

              If in fact The Planet had powered up their generators, they'd have fried a lot more stuff and caused more fire. The may have destroyed their chances of salvaging the grid within 48 hours at all. Why? It turns out (we now know) that the force of the initial explosion moved three walls in the power distribution center more than a foot (I heard 3 feet I think) off their base. This tore out electrical connections, cables, conduits and power switches. Just now, after 28 hours, they've figured out how to get power to the servers on the second floor, but for the first floor servers they're having to rig up a line from the generators to that floor and it will take until tomorrow to do that. Why? Because the electrical connections from that distribution room to the first floor servers are destroyed. They're going to be running 3000 servers on the first floor off those generators for a week while they get the equipment to rebuild the connectivity to the main distribution room.

              What does this prove?

              1. It proves the fire marshal was right in not allowing them to feed power in their.

              2. It proves that when that big dumb fireman you see (who may be a volunteer who's also a network guy and software developer with an IQ above 95% of the world) may in fact have a good reason for the way they do things on scene.

              Look, as a firefighter I don't set out to ruin someone's day. I set out to keep them safe. If that sounds paternalistic, well, It is paternalistic. It very much feels that way. In my small town, its how I feel. I wonder ever time I walk into a building, how I would protect MY PEOPLE in this building if a fire broke out or a hazmat incident started or whatever. You can't help it, its what you're trained to do.

  • My servers dropped off the net yesterday afternoon, and if all goes well they'll be up and running late tonight. At 1700PST they're supposed to do a power test, then start bringing up the environmentals, the switching gear, and blocks of servers.

    My thoughts as a customer of theirs:

    1. Good updates. Not as frequent or clear as I'd like, but mostly they didn't have much to add.

    2. Anyone bitching about the thousands of dollars per hour they're losing has not credibility to me. If your junk is that important, your hot standby server should be in another data center.

    3. This is a very rare event, and I will not be pulling out of what has been an excellent relationship so far with them.

    4. I am adding a fail over server in another data center (their Dallas facility). I'd planned this already but got caught being too slow this time.

    5. Because of the incident, I will probably make the new Dallas server the primary and the existing Houston one the backup. This is because I think there will be long term stability issues in this Houston data center for months to come. I know what concrete, drywall, and fire extinguisher dust does to servers. I also know they'll have a lot of work in reconstruction ahead, and that can lead to other issues.

    For now, I'll wait it out. I've heard of this cool place called "outside". maybe I'll check it out.
    • Re: (Score:3, Insightful)

      Only a few people need to have a lot of servers for there to be 18 servers for every 15 customers. To be honest, I'm surprised the ratio is so low, I would have guessed most hosting in a similar environment would be by people who'd want at least 2 servers for redundancy/backup/speed reasons...
      • Wouldn't people who want such redundancy consider putting the other server in another DC?
          • Yep (Score:4, Insightful)

            by Sycraft-fu (314770) on Monday June 02 2008, @01:50AM (#23623877)
            For example someone like Newegg.com probably has a redundant data centre. Reason being that if their site is down, their income drops to 0. Even if they had the phone techs to do the orders nobody knows their phone number and since the site is down, you can't look it up. However someone like Rotel.com probably doesn't. If their site is down it's inconvenient, and might possibly cost them some sales from people who can't research their products online, but ultimately it isn't a big deal even if it's gone for a couple of days. Thus it isn't so likely they'd spend the money on being in different data centres.

            You are also right on in terms of type of failure. I've been at the whole computer support business for quite a while now, and I have a lot of friends who do the same thing. I don't know that I could count the number of servers that I've seen die. I wouldn't call it a common occurrence, but it happens often enough that it is a real concern and thus important servers tend to have backups. However I've never heard of a data centre being taken out (I mean from someone I know personally, I've seen it on the news). Even when a UPS blew up in the university's main data centre, it didn't end up having to go down.

            I'm willing to bet that if you were able to get statistics on the whole of the US, you'd find my little sample is quite true. There'd be a lot of cases of servers dying, but very, very few of whole data centres going down, and then usually only because of things like hurricanes or the 9/11 attacks. Thus, a backup server makes sense, however unless it is really important a backup data centre may not.
    • by p0tat03 (985078) on Sunday June 01 2008, @01:42PM (#23619011)
      ThePlanet is a popular host for hosting resellers. Many of the no-name shared hosting providers out there host at ThePlanet, amongst other places. So... Many of these customers would be individuals (or very small companies), who in turn dole out space/bandwidth to their own clients. The total number of customers affected can be 10-20x the number reported because of this.
    • by Hijacked Public (999535) on Sunday June 01 2008, @01:37PM (#23618965)

      It is often the case that transformers are kept apart from all other components
      And that appears to have been the case here. Had you read the article, or even the unusually accurate headline, you would know that the 9,000 servers were 'dropped' rather than 'blown apart'. They are still physically with us, they are just dropped from service because they don't have any power because the power supply blew up.

      Further, the 9,000 servers were physically, geographically, isolated enough from the power supply (which is what exploded) to be protected. We know this to be the case because we read the article and headline and understood them and they indicate that the 9,000 servers were not blown up.

      To put it another way, only the power supply was damaged by the explosion, the servers were not. Probably there was no way to isolate the power from its own explosion. The servers, however, we protected.

      So, in summary, the 9,000 servers were not blown up. Only the power.

      The power is off due to the explosion but there servers themselves are A-OK.
      • Correction (Score:5, Informative)

        by Gazzonyx (982402) on Sunday June 01 2008, @02:00PM (#23619171)
        Sorry for replying to myself, I don't think I made my post clear; the backup power is not on (the mains was blown to bits), because the fire department told them to shut it off.
      • by cecil_turtle (820519) on Sunday June 01 2008, @02:38PM (#23619461)
        ThePlanet has 5 or more datacenters. The cost and complexity of doing a full blown physically separated 2N power system at every datacenter is far more expensive than taking the chance of having to issue a credit against an SLA. Not to mention that when a fire is involved, the fire department has full authority and may instruct you to cut all power anyway - they are coming in to an unknown situation and won't risk their own people just because you say the other power system is isolated.

        Another issue is the complexity of a full blown 2N power system is likely to cause more outages due to human error during routine maintenance over an N+1 system. Complete 2N power systems from grid and backup sources all the way to the servers with no single point of failure (transformers, wiring, switching, PDUs, UPSs, etc.) are enormously complex and expensive, so it's not "the only thing that makes sense". I assure you issuing a one-day pro-rated credit to all your customers is cheaper.
            • by njcoder (657816) on Sunday June 01 2008, @05:05PM (#23620571)

              Part of my point that you apparently missed was that even a full 2N power system end-to-end doesn't guarantee uptime. There are very few - and I'd even go so far as to say "if any" - datacenters in the world that could handle an explosion / fire without going down.
              The dc didn't explode, just the power room. It seems there was just one power room. I've been to data centers around here, even small ones that have 2 power rooms.

              While it may be the fire dept that is erroneously preventing them from bringing up their back-up power, it's part of a poor disaster recovery plan to not engage with the fire dept, electric co, etc. before a disaster happens, so that everyone is on-board with your disaster recovery plans and that you have the ability to implement that plan.

              The explosion was isolated to the power room. The servers are fine, the backup generators and batteries are fine. The servers should have been back online if they had a good disaster recovery plan. The whole point of disaster recovery is being able to handle a disaster. You can't say "oh there was a disaster, you can't help that". This is exactly what their plan should have been able to handle. The power room goes offline. It shouldn't matter if it was because of an explosion, a fire, equipment failure or being beamed into outer space.

              It also shouldn't matter who is telling them to keep the power off. Part of the disaster recovery plan should have been making sure local authorities allowed them to carry it out. Fine, they have to shut off all power when firemen are in there with hoses. I understand that. But once the fire is out your plan should allow you to bring up backup power. It didn't. So I don't see how they can call themselves a "World Class Data Center". Part of what they sell and what customers expect is disaster recovery. And there are data centers that can provide this.

              ThePlanet is pretty cheap compared to datacenters like NAC that have more redundancy and security. But ThePlanet wants to advertise that they are just as good. Now they were caught with their pants down when there was actually a disaster and their disaster recovery plan failed.
    • by aronschatz (570456) on Sunday June 01 2008, @07:28PM (#23621645) Homepage
      Yeah, because everyone can afford redundancy like you can.

      Most people own a single server that they make backups of in case of it crashing OR have two servers in the same datacenter in case one fails.

      I don't know how you can easily do offsite switch over without a huge infrastructure to support it which most people don't have the time and money to do.

      Get off your high horse.